The State and you
How to get a building permit in Benin?
The building permit is issued by the commune, with an announced time of 25 to 30 days at most and a fully online procedure in four communes. Three categories determine the documents required.
Unofficial English translation of the French page: the French text prevails. Read the French version.

- Steps
- 4
- Observed lead time
- announced: 25 to 30 days maximum
Who it is for and why
The building permit (permis de construire) is the administrative decision that authorises, on the basis of urban planning rules, new constructions, the modification of unfinished construction works and the regularisation of works undertaken without authorisation. Any natural person or legal entity can apply: a trader building a shop, a craftsman a workshop, a company a warehouse. The commune issues the permit; the basic text is Decree No. 2020-056 of 5 February 2020.
There are three categories, according to risk: A for low-risk constructions, B for medium risk, C for high risk. Order No. 47 of 2020 sets the categorisation. The category determines the documents to provide and the fee rate.
What you need
- Basic file, written documents: an application form (identity and capacity of the applicant, location and area of the plot, intended use of the building, ground footprint, floor area); the title deed or a document presumptive of ownership (land title, certificate confirming rights, or resettlement certificate: titre foncier, attestation de confirmation des droits, attestation de recasement); a descriptive specification (devis descriptif), with the planned materials, how they will be implemented and the method of execution, and a cost estimate of the works (devis estimatif); a statement of responsibility signed by the approved private architect registered on the roll of the National Order of Architects and Urban Planners of Benin; a statement of responsibility signed by the private civil engineer.
- Basic file, drawings: a site location plan; a site plan; a layout plan of the existing situation, if there are already structures on the site; the building project at a scale of 1/200, 1/100 or 1/50, with plan views of each level, at least two sections including one through the stairs, if any, and the façades; a detailed plan of the drainage and sanitation works; detailed structural plans; the receipt for payment of the fee; proof of payment of the study fees.
- In addition for categories B and C: a fire safety report with plan; a copy of the environmental compliance certificate, when the project is likely to harm the environment; a report on accessibility for people with reduced mobility, if it is an establishment open to the public; a soil study report from an approved laboratory; structural calculation notes signed by a civil engineer.
- In addition for category C: a works execution methodology that takes construction site regulations into account.
- Official fees, separate from any other cost: the fee is calculated per square metre of gross floor area of all floors, at a rate that varies by category. The scales are on the portal page cited in the sources.
The page adds that, exceptionally, additional documents may be requested if they are essential to understanding the project.
The steps
Check that your project requires a permit
Decree No. 2022-418 of 20 July 2022 rewrote Article 9 of the 2020 decree, which lists the works not subject to a permit. They include: interior modifications that do not change the intended use of the structure, create no new level and affect neither stability nor the façade; façade renovation work and minor acts, the list of which is set by order of the mayor according to the commune’s zoning; the installation of signs and advertisements; terraces that do not exceed 2.5 m above ground; boundary walls less than 2 metres high, without prejudice to the specific regime governing fences; and, in special economic zones and industrial free zones, certain warehouses with a light metal-frame roof (10 m maximum height, 50 x 200 m² at most), subject to inspection by the national commission for urban planning authorisations.
The list of “minor acts” depends on the commune.
- Where: https://sgg.gouv.bj/doc/decret-2022-418/download
Identify the category and build the file
The category (A, B or C) sets the list of documents. The portal provides three forms: the application for a permit for a residential building, the application for an urban planning certificate (certificat d’urbanisme) and the application for a permit for an establishment open to the public (établissement recevant du public, ERP). The statements of responsibility require an architect registered with the Order and a civil engineer.
For category C, the list is that of category B, supplemented by a works execution methodology.
- Where: https://service-public.bj/public/services/service/PS00141
Submit the application
For the communes of Cotonou, Parakou, Abomey-Calavi and Porto-Novo, the portal describes a fully dematerialised procedure: file assembly and submission online, online payment, online tracking with requests for additional information, online decision, online collection of the permit.
The CatIS catalogue describes the following steps: assembling the file according to the category, online payment, submitting the file, collection. It names as the competent service the one-stop desk of the regulations department of the Directorate of Legal and Land Affairs of the town hall of the commune concerned. The service locations cited by the portal are Cotonou, Porto-Novo, Abomey-Calavi, Allada, Natitingou and Matéri. The hours are Monday to Friday, from 8:00 a.m. to 12:30 p.m. in the morning; in the afternoon, from 2:00 p.m. to 5:30 p.m. according to the portal, from 3:00 p.m. to 6:30 p.m. according to the catalogue.
- Where: Guichet unique du service réglementation de la Direction des affaires juridiques et du foncier de la mairie de la commune concernée (one-stop desk of the regulations department, Directorate of Legal and Land Affairs, town hall of the commune concerned)
- Cost: Fee per square metre of gross floor area of all floors, by category (scale on the portal page)
Track the file and collect the permit
The estimated duration is “variable, 25 to 30 days maximum”, with a reference to the decree for details. In the four communes cited, tracking the file (with requests for additional information), the decision and the collection of the permit are done online according to the portal. The information points cited are the town halls, the prefectures, the departmental directorates in charge of housing and urban planning, the General Directorate of Housing and Construction, the Order of Architects and the Government’s website (gouv.bj).
- Where: Mairie de la commune concernée (town hall of the commune concerned)
- Observed time: announced: 25 to 30 days maximum
The pitfalls
- Filing without a registered architect or an engineer. The two statements of responsibility are part of the basic file.
- Forgetting the proofs of payment. The fee receipt and proof of payment of the study fees are on the list.
- Neglecting the soil study. For categories B and C, the report must come from a laboratory approved in the Republic of Benin.
- Confusing B and C. Category C takes the list of category B and adds the works execution methodology.
- Assuming a small project is exempt. The list of minor works is set by the mayor according to zoning: it varies from one commune to another.
- Counting on the 25 to 30 days as a guarantee. The portal announces them “at most” and refers to the decree for details.
Frequently asked questions
Can the application be made online?
The portal describes a fully dematerialised procedure for the communes of Cotonou, Parakou, Abomey-Calavi and Porto-Novo.
How long does processing take?
Announced: 25 to 30 days maximum, with a reference to the decree for details.
Who can apply for a building permit?
Any natural person or legal entity, according to the portal.
Does a boundary wall require a permit?
Decree No. 2022-418 exempts boundary walls less than 2 metres high, without prejudice to the specific regime governing fences.
Can a building constructed without a permit be regularised?
Yes: the building permit is also used to regularise works undertaken without authorisation, according to the portal’s definition.