How to connect a small business to electricity and water?

SBEE’s electricity connection for SMEs and SMIs is presented as free, within 36 days at most; for water connections for legal entities, SONEB announces 1 to 10 business days.

Unofficial English translation of the French page: the French text prevails. Read the French version.

Workers in safety vests around a large cable reel on a worksite, on a street in Benin (illustrative photo).
©

Photo: HuboBelton / Wikimedia Commons, CC BY-SA 4.0 (cropped image) · All credits

Steps
5
Official fees
Electricity: 0 FCFA for SMEs and SMIs that meet the conditions (SBEE page); water: free for SMEs and SMIs, 2,360 FCFA for other applicants (portal, PS00667)
Observed lead time
announced: 36 calendar days at most for electricity; 1 to 10 business days for water depending on the file

Who it is for and why

A workshop, a shop or a small production unit gets its electricity meter and its water connection through two separate services: the connection of SMEs and SMIs (PME and PMI) to the grid of the Benin Electric Energy Company (SBEE), a three-step programme, and the water connection of legal entities with the National Water Company of Benin (SONEB).

Both procedures start online, and the conditions are not the same: the first is aimed at a specific category of businesses and a given power level, the second at any organisation established in Benin.

What you need

  • Electricity (SBEE), according to the portal: be an SME or SMI duly registered in Benin; have installations at most 150 m from the SBEE grid; have a power load (bilan de puissance) between 140 and 160 kVA; if the grid is underground, have a transformer cabin (cabine) that complies with the SBEE’s plan; be able to consume from commissioning.
  • Water (SONEB), portal list: a sketch of the access plan (a hand-drawn plan with a written explanation), a copy of an identity document, a copy of the title deed of the plot to be supplied, the manager’s letter (the portal writes “habileté”), and a form titled “numérisation.pdf”.
  • Water, SONEB page on free connection for businesses: be a business that owns the building, has a building permit or whose permit is being prepared, located in the immediate vicinity of the SONEB water network; prepare in JPEG the trade register entry (front and back) and the sketch of the access plan.
  • Official fees, separate from any other cost: free service is a benefit of these programmes, reserved for SMEs and SMIs that meet the criteria above. Electricity: the portal states “free” (gratuit) and the SBEE page shows 0 FCFA at each of the three steps. Water: the connection application is free for SMEs and SMIs; for other applicants, the portal shows a cost of 2,360 FCFA.

The steps

  1. Check that your business falls within the electricity programme

    The portal’s conditions target SMEs and SMIs whose power load is between 140 and 160 kVA. The SBEE presents on its own website a “special SME/SMI programme from 50 to 250 kVA”, which repeats the same three steps and the same times. The SBEE page asks for the trade register entry, the unique tax identifier (IFU) or the personal identification number (NPI), and the national identity card.

    For water, there is no power category: the service is aimed, according to the portal, at anyone with an organisation in Benin’s territory.

    • Where: https://sbee.bj/professionnels/conditions-programme-special-pme-pmi-de-50-a-250-kva/
  2. Apply for the electricity connection online

    The application is made on the SBEE’s website. It takes one calendar day, according to the portal, which says it is free under the programme. The technical teams of the SBEE and CONTRELEC are automatically notified: the presence of the customer or their representative is not required during their visit.

    • Where: https://www.sbee.bj
    • Observed time: announced: 1 calendar day
    • Cost: Free, 0 FCFA, for SMEs and SMIs that meet the programme’s conditions (PS00261, SBEE page)
  3. Pass the compliance inspection and sign the contract

    CONTRELEC checks the compliance of the interior installations, the SBEE that of the exterior installations. You then receive the eligibility notification by e-mail, and you sign the contract.

    • Where: Direction générale de la SBEE, Ganhi (01 BP 123)
    • Observed time: announced: 14 calendar days
    • Cost: 0 FCFA for SMEs and SMIs that meet the programme’s conditions (SBEE page)
  4. Wait for the transformer to be installed and for commissioning

    The SBEE installs the transformer at the customer’s premises, connects the premises to the grid and commissions the supply. The portal announces 21 calendar days for this step. Added end to end, 1 + 14 + 21 days make the announced 36 days.

    According to an article on the government’s website dated 3 May 2021, there is no longer a deposit (advance on consumption) for needs of 140 to 160 kVA.

    • Where: https://www.gouv.bj/article/1261/acces-electricite-benin---connecter-votre-zero-franc/
    • Observed time: announced: 21 calendar days
    • Cost: 0 FCFA for SMEs and SMIs that meet the programme’s conditions (SBEE page)
  5. Apply for the water connection from SONEB

    The portal summarises the procedure as follows: application and payment online, then an agent contacts you. The announced times depend on the file: 1 business day for SMEs and SMIs, 5 business days for ordinary quotes, 10 business days for quotes with network extension. The days in this step are business days, those for electricity are calendar days: do not add them up without converting them.

    According to the portal, the application includes an identity document and a title deed for the plot. According to the SONEB page on free connection, it includes the trade register entry, and the manager’s handwritten signature is traced on screen, in the form: a scanned signature is not accepted. Both ask for the sketch of the access plan.

    • Where: SONEB, 92 avenue du Pape Jean-Paul II, Cotonou (01 BP 216 RP); https://service-public.bj/public/services/service/PS00667
    • Observed time: announced: 1 business day (SMEs/SMIs), 5 business days (ordinary quotes), 10 business days (quotes with extension)
    • Cost: Free for SMEs and SMIs; 2,360 FCFA for other applicants (PS00667)

The pitfalls

  • Confusing the two power ranges. The portal states 140 to 160 kVA; the SBEE presents a programme of 50 to 250 kVA.
  • Neglecting the distance. The portal sets the limit at 150 m from the SBEE grid.
  • Forgetting the transformer cabin on an underground grid. If the grid is underground, the developer must have a transformer cabin that complies with the SBEE’s plan.
  • Applying for the connection before being ready to consume. This is a condition of use written on the page: be able to consume from commissioning.
  • Adding calendar days and business days. Electricity counts in calendar days, water in business days.
  • Preparing a single document list for water. The portal and the SONEB page do not ask for exactly the same documents.

Frequently asked questions

How much does it cost to connect a small business?

Electricity: free for SMEs and SMIs that meet the programme’s conditions; the portal states “free” and the SBEE page shows 0 FCFA for each of the three steps. Water: the connection application is free for SMEs and SMIs; for other applicants, the portal shows a cost of 2,360 FCFA.

What power level is needed for the free connection?

The portal states a power load between 140 and 160 kVA. The SBEE, for its part, presents a programme for 50 to 250 kVA.

How long does a water connection take?

Times announced by the portal: 1 business day for SMEs and SMIs, 5 business days for ordinary quotes, 10 business days for quotes with network extension.

Can a tenant apply for a water connection?

Both pages ask for proof of ownership: a title deed for the plot on the portal, a business that owns the building on the SONEB page.

Do I need to be present at the SBEE inspection?

No, according to the portal: the presence of the customer or their representative is not required during the compliance check.